BRIGHTON & HOVE CITY COUNCIL
Cabinet
10.30am 12 November 2026
Council Chamber, Hove Town Hall
decision list
|
Part One |
|
1
|
Brighton Marina to River Adur Flood and Coastal Erosion Risk Management (FCERM) scheme
Decision implemented at close of business on: 20 November 2026 unless called in
|
||
|
|
Ward Affected: |
All Wards |
|
|
|
1. That Cabinet approves the commencement of an open procurement process for Phase 3 construction works of the Scheme with an estimated contract value of approximately £13.5 million, with the procurement undertaken by Brighton & Hove City Council in its capacity as Lead Authority for the Scheme and in consultation with the Cabinet Member for Transport and City Infrastructure.
2. That Cabinet confirms Brighton and Hove City Council’s continuing role as Lead Authority for the Scheme and delegates authority to the Corporate Director, City Operations, in consultation with the Cabinet Member for Transport and City Infrastructure, to: · take all steps necessary to enter into any partnership, funding or delivery agreements required to facilitate Phase 3 and complete the Scheme. · evaluate tenders and award the Phase 3 construction contract; and, · enter into any associated contracts, warranties, deeds and ancillary documentation.
3. That Cabinet approves the revision of Brighton & Hove City Council's capital contribution to the Scheme from £11 million to £4.5 million, reflecting updated funding arrangements and increased Environment Agency Grant in Aid allocations.
4. That Cabinet approves an increase in capital budget of £9.8m funded by Grant in Aid and external contributions from Shoreham Port Authority.
|
||
|
1
|
Managing the Transport Network
Decision implemented at close of business on: 20 November 2026 unless called in
|
||
|
|
Contact Officer: |
Tracy Beverley |
Tel: 01273 292813 |
|
|
Ward Affected: |
All Wards |
|
|
|
1. That Cabinet notes the outcome of consultation on the first five Moving Traffic Enforcement locations, (outlined in section 3 and detailed in Appendix 2) and approves the implementation of Moving Traffic Enforcement at those locations.
2. That Cabinet approves the strategic approach to the identification, prioritisation, consultation, implementation and review of Moving Traffic Enforcement locations, summarised in section 3 and set out in Appendix 1.
3. That Cabinet delegates authority to the Corporate Director for City Operations to approve and implement future Moving Traffic Enforcement locations in consultation with the lead Member for Transport.
4. That Cabinet notes the updates on School Streets, Lane Rental, the Digital Twin project and anticipated pavement-parking enforcement powers set out in section 3 of this report.
|
||
|
1
|
School Admission Arrangements 2028-29
Decision implemented at close of business on: 20 November 2026 unless called in
|
||
|
|
Contact Officer: |
Richard Barker |
Tel: 01273 290732 |
|
|
Ward Affected: |
All Wards |
|
|
|
1. Cabinet agrees to make no changes to the council’s admission arrangements other than the changes listed below.
2. Cabinet agrees to consult upon a change to the Published Admission Number (PAN) of Brunswick Primary School from 90 to 60 pupils from September 2028.
3. Cabinet agrees to consult upon a change to the Published Admission Number (PAN) of Coldean Primary School from 60 to 30 pupils from September 2028.
4. Cabinet agrees to note the binding decision of the Schools Adjudicator in determining the secondary school admission arrangements for September 2027, that inform the arrangements in place for September 2028. Including clarification on the category of Free School Meals eligible for priority and the proportion of places available, following changes introduced by the Department for Education in the summer after the arrangements were determined by Full Council in January 2026.
5. Cabinet agrees to consult on the Primary and Secondary coordinated schemes and to make no changes to the “relevant area”.
|
||
|
1
|
Homes for everyone: homelessness and rough sleeping local delivery plan
Decision implemented at close of business on: 20 November 2026 unless called in
|
||
|
|
Ward Affected: |
All Wards |
|
|
|
1. Cabinet agrees to adopt and publish: · the Homelessness and Rough Sleeping Action Plans (Appendix 1) · the Policy for Ensuring the Suitability of Temporary Accommodation (Appendix 2) · the Long-Term Rough Sleeping Partnership Plan (Appendix 3)
2. Cabinet delegates to the Corporate Director, Homes and Adult Social Care, in consultation with the Cabinet Member for Housing, the authority to review and amend actions and targets contained within the Homelessness and Rough Sleeping Action Plans and Long-Term Rough Sleeping Partnership Plan for the duration of the Action Plans.
|
||
|
1
|
Expanding Council Controlled Temporary Accommodation
Decision implemented at close of business on: 20 November 2026 unless called in
|
||
|
|
Contact Officer: |
Diane Hughes |
Tel: 01273 293159 |
|
|
Ward Affected: |
All Wards |
|
|
|
1. Cabinet approves the three-year Council controlled Temporary Accommodation Supply Programme delivering up to 500 homes from April 2027. This will be delivered through a flexible mix of acquisitions and long leasing arrangements.
2. Cabinet agree £110,000 revenue funding to prepare the business case for the establishment of a bulk leasing programme.
3. Cabinet to note that a further report will be brought to a future Cabinet meeting to seek agreement to the proposed new leasing arrangements as set out at Section 6.
4. Cabinet delegates authority to the Corporate Director Homes & Adult Social Care to take the steps necessary to agree future acquisitions for the supply of affordable housing in consultation with: · the Cabinet Member for Housing, for acquisitions with a value between £500k and £3 million. · the Cabinet Member for Housing, the Cabinet Member for Finance and City Regeneration and the Director for Finance and Property, for acquisitions with a value between £3 million and £10million.
5. Cabinet agrees an additional HRA budget of £24.324m to support the continued buy back of properties in the financial year 2026/27.
|
||
|
1
|
Targeted Budget Management (TBM) 2026/27 Month 6 (September)
Decision implemented at close of business on: unless called in
|
||
|
|
Ward Affected: |
All Wards |
|
|
|
1. Cabinet notes the forecast risk position for the General Fund, which indicates a potential forecast overspend risk of £26.446m.
2. Cabinet notes the additional risks of £13.836m included in the table at Appendix 2 which are not included in the forecast figure above. 3. Cabinet notes the forecast overspend risk for the separate Housing Revenue Account (HRA), which is an overspend of £0.683m.
4. Cabinet notes the forecast overspend risk for the ring-fenced Dedicated Schools Grant, which is an overspend of £6.672m in-year, resulting in a cumulative deficit of £6.848m.
5. Cabinet notes the progress of transformation programmes shown in Appendix 4 and the delivery of savings as detailed at 3.11 and 3.12 of the report.
6. Cabinet notes the aged debt position shown at Appendix 3.
7. Cabinet notes the forecast collection fund position detailed in 3.15 and 3.16.
|
||
|
1
|
Large Panel System Housing Masterplan and Land Assembly
Decision implemented at close of business on: 20 November 2026 unless called in
|
||
|
|
Ward Affected: |
All Wards |
|
|
|
1. Note the progress of the LPS Redevelopment Programme, including the service of Initial Demolition Notices on all secure council tenants in the eight LPS blocks; St James’s House, Nettleton Court, Dudeney Lodge, Falcon Court, Heron Court, Kestrel Court, Kingfisher Court, and Swallow Court, pursuant to paragraph 4(2) of Schedule 5A of the Housing Act 1985 (as amended).
2. Note the suspension of letting secure tenancies at the eight LPS blocks; St James’s House, Nettleton Court, Dudeney Lodge, Falcon Court, Heron Court, Kestrel Court, Kingfisher Court, and Swallow Court.
3. Note the temporary use of void properties in the LPS buildings as Temporary Accommodation (TA) and agree to delegate authority to the Corporate Director Homes & Adult Social Care in consultation with the Cabinet Member for Housing to determine when new TA lettings should cease, and to determine the timing of service of the Notice to Quit (NTQ) on TA households, or any other process required to enable vacant possession of the properties where needed.
4. Agree to delegate authority to the Corporate Director Homes and Adult in consultation with the Cabinet Member for Housing Social Care to determine when to serve the Notice of Seeking Possession (NOSP) on the secure council tenants.
5. Approve the suggested amendments to the sections of the Local Lettings Plan for Large Panel System (LPS) blocks and the Rehousing Policy – Regeneration Schemes as set out at paragraphs 4.2 and 4.3 of this report and agree to delegate authority to the Corporate Director Homes and Adult Social Care in consultation with the Cabinet Member for Housing to create a policy for Secure Council Tenants with an Interest in Returning and return to a future Cabinet to approve the policy. Also, to include any properties not previously covered by the LPS Local Lettings Plan in the Plan following the extended redevelopment footprint and update any other aspects of the Rehousing Policy – Regeneration Schemes or LPS Local Lettings Plan as may be required.
6. Agree to delegate authority to the Corporate Director Homes and Adult Social Care in consultation with the Cabinet Member for Housing of a ‘leaseholder assistance’ bespoke offer and a budget of £0.1m where required for specific exceptional cases of resident leaseholder financial hardship and/or vulnerability requiring support.
7. Note that the intention is to permanently close the Chapel Street public pay and-display car park beneath St. James’ House, subject to the outcome of the relevant Traffic Regulation Order process.
8. Agree to delegate authority to the Corporate Director Homes & Adult Social Care in consultation with the Cabinet Member for Housing to consider Section 105 of Housing Act 1985 consultation responses from consultees of the surrounding land and council owned property potentially to be included in the extended LPS development proposal areas, including for demolition/construction site set up, opportunities for phased redevelopment and landscaping.
9. Note the opportunity to extend the redevelopment area for the Dudeney and Nettleton site (extending beyond just the LPS blocks and land) and agree to delegate authority to the Corporate Director Homes & Adult Social Care in consultation with the Cabinet Member for Housing to consider land assembly requirements and approve the acquisition of property where required in accordance with Part 1 and Part 2 reports.
10. Note the Section 105 of the Housing Act 1985 consultation response from the secure tenant of the proposed additional land assembly (Hollingdean) set out in the part 2 report and approve that the secure council tenant is to be given the provisions of the Rehousing Policy – Regeneration Schemes and LPS Local Lettings Plan.
11. Approve the service of an Initial Demolition Notice to any council owned property with secure council tenants in the extended redevelopment area referred to at recommendation 2.9.
12. Approve an additional capital budget of £1.46m to support staff resourcing, land assembly costs, home loss and disturbance costs for secure council tenants of properties in the extended redevelopment areas, ‘leaseholder assistance’ contingency, legal costs and the appointment of an Independent Tenant and Leaseholder Adviser for the residents of the three LPS redevelopment areas.
13. Approve the progression of an optimized approach to the design of the redevelopment proposals and masterplans.
|
||
|
1
|
Large Panel System Housing Masterplan and Land Assembly (Exempt Category 3)
|
||
|
|
Ward Affected: |
All Wards |
|