Decision - Large Panel System Housing Masterplan and Land Assembly

skip navigation and tools

Decision details

Large Panel System Housing Masterplan and Land Assembly

Decision Maker: Cabinet

Decision status: Recommendations Approved (subject to call-in)

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Cabinet is asked to approve the LPS Masterplan approach and land assembly opportunities.

Decision:

1.       Note the progress of the LPS Redevelopment Programme, including the service of Initial Demolition Notices on all secure council tenants in the eight LPS blocks; St James’s House, Nettleton Court, Dudeney Lodge, Falcon Court, Heron Court, Kestrel Court, Kingfisher Court, and Swallow Court, pursuant to paragraph 4(2) of Schedule 5A of the Housing Act 1985 (as amended).

 

2.       Note the suspension of letting secure tenancies at the eight LPS blocks; St James’s House, Nettleton Court, Dudeney Lodge, Falcon Court, Heron Court, Kestrel Court, Kingfisher Court, and Swallow Court.

 

3.       Note the temporary use of void properties in the LPS buildings as Temporary Accommodation (TA) and agree to delegate authority to the Corporate Director Homes & Adult Social Care in consultation with the Cabinet Member for Housing to determine when new TA lettings should cease, and to determine the timing of service of the Notice to Quit (NTQ) on TA households, or any other process required to enable vacant possession of the properties where needed.

 

4.       Agree to delegate authority to the Corporate Director Homes and Adult in consultation with the Cabinet Member for Housing Social Care to determine when to serve the Notice of Seeking Possession (NOSP) on the secure council tenants.

 

5.       Approve the suggested amendments to the sections of the Local Lettings Plan for Large Panel System (LPS) blocks and the Rehousing Policy – Regeneration Schemes as set out at paragraphs 4.2 and 4.3 of this report and agree to delegate authority to the Corporate Director Homes and Adult Social Care in consultation with the Cabinet Member for Housing to create a policy for Secure Council Tenants with an Interest in Returning and return to a future Cabinet to approve the policy. Also, to include any properties not previously covered by the LPS Local Lettings Plan in the Plan following the extended redevelopment footprint and update any other aspects of the Rehousing Policy – Regeneration Schemes or LPS Local Lettings Plan as may be required.

 

6.       Agree to delegate authority to the Corporate Director Homes and Adult Social Care in consultation with the Cabinet Member for Housing of a ‘leaseholder assistance’ bespoke offer and a budget of £0.1m where required for specific exceptional cases of resident leaseholder financial hardship and/or vulnerability requiring support.

 

7.       Note that the intention is to permanently close the Chapel Street public pay and-display car park beneath St. James’ House, subject to the outcome of the relevant Traffic Regulation Order process.

 

8.       Agree to delegate authority to the Corporate Director Homes & Adult Social Care in consultation with the Cabinet Member for Housing to consider Section 105 of Housing Act 1985 consultation responses from consultees of the surrounding land and council owned property potentially to be included in the extended LPS development proposal areas, including for demolition/construction site set up, opportunities for phased redevelopment and landscaping.

 

9.       Note the opportunity to extend the redevelopment area for the Dudeney and Nettleton site (extending beyond just the LPS blocks and land) and agree to delegate authority to the Corporate Director Homes & Adult Social Care in consultation with the Cabinet Member for Housing to consider land assembly requirements and approve the acquisition of property where required in accordance with Part 1 and Part 2 reports.

 

10.     Note the Section 105 of the Housing Act 1985 consultation response from the secure tenant of the proposed additional land assembly (Hollingdean) set out in the part 2 report and approve that the secure council tenant is to be given the provisions of the Rehousing Policy – Regeneration Schemes and LPS Local Lettings Plan.

 

11.     Approve the service of an Initial Demolition Notice to any council owned property with secure council tenants in the extended redevelopment area referred to at recommendation 2.9.

 

12.     Approve an additional capital budget of £1.46m to support staff resourcing, land assembly costs, home loss and disturbance costs for secure council tenants of properties in the extended redevelopment areas, ‘leaseholder assistance’ contingency, legal costs and the appointment of an Independent Tenant and Leaseholder Adviser for the residents of the three LPS redevelopment areas.

 

13.     Approve the progression of an optimized approach to the design of the redevelopment proposals and masterplans.

Report author: Paul Dalton

Publication date: 13/11/2026

Date of decision: 12/11/2026

Decided at meeting: 12/11/2026 - Cabinet

Date comes into force if not called in: 21/11/2026

Call-in deadline date: 20/11/2026

Current call-in Count: 0

Accompanying Documents:

 