Decision - Accommodation Strategy - Update and Proposals
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Accommodation Strategy - Update and Proposals
Decision Maker: Cabinet (pre 2012)
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
To give an update on the corporate accommodation strategy and proposals, seeking approval of the principles for the next phase of the strategy and ‘spend to save’ project involving the re-location to Bartholomew House and other related buildings.
Decision:
(1) That Cabinet notes the proposed next steps in the corporate Accommodation Strategy.
(2) That Cabinet approves the outline business case for the proposed exit of Priory House and the re-location of services to Bartholomew House and other subsidiary buildings.
(3) That Cabinet approves the creation of a unified public walk-in access point for council services in the centre of Brighton at Bartholomew House.
(4) That Cabinet authorises the further development of the detailed business case, detailed design and preparatory works.
(5) That Cabinet requests a further report on the implementation of the proposals following consultations and detailed business case preparation.
Reasons for the decision:
To approve the next phase of the accommodation strategy, the spend to save project, the outline business case, the initial project implementation programme and the developing accommodation principles and standards set out in the Appendices.
Alternative options considered:
1. No change – The findings of the Customer Access vision improving the customer experience are not implemented and the Housing Benefits and Revenues, Access Services and Business Support teams remain in Priory House. The lease break is not exercised, savings are not achieved and the lease obligations and liabilities continue until the end of the lease in 2016. This option exposes the council to future added risk of continuing lease costs that will be subject to external market forces and does not enable the council to benefit from the potential protection from the uncertain property market conditions and the consolidation into our own buildings.
2. Change Option 1- The Housing Benefits Team is the largest of the three teams affected by the potential relocation from Priory House. One option considered was to form a new office in the undercroft at Kings House, however this would provide only about 90-100 desk spaces (up to 180 are required) and would mean splitting the team over two sites. There would also be a consequential loss of car parking at Kings House. This option was not explored further as there would be considerable disadvantages in splitting the Housing Benefits team over two sites. This is also contrary to the accommodation strategy which aims, where possible to bring disparate teams together onto single sites.
3. Change Option2 – Consider the construction of a mansard extension on the fourth floor of Barts House. This would involve considerable extra capital investment in the construction of the mansard roof to accommodate a relatively small percentage of staff – approx 40 no.
Report author: Angela Dymott, Nigel McCutcheon
Publication date: 14/01/2010
Date of decision: 14/01/2010
Decided at meeting: 14/01/2010 - Cabinet (pre 2012)
Effective from: 22/01/2010
Accompanying Documents: