Mercury Abatement at Woodvale Crematorium
Decision Maker: Cabinet (pre 2012)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
As a crematorium owner, BHCC is obliged to comply with mercury emissions legislation which becomes effective from 31 December 2012. This report explains the procurement process and outlines options for Cabinet to decide on the way forward.
Decision:
RESOLVED:
(1) That the proposal for replacement of old and antiquated plant and the introduction of mercury abatement measures via an OJEU compliant tender process be approved;
(2) That the Strategic Director of Resources, be granted delegated authority, in consultation with the Cabinet Member for Finance & Central Services, to approve the purchase and installation of new equipment up to a value of £1.2m procured directly through an OJEU compliant route; and
(3) That the funding of £1.2m from the council’s Capital Investment Programme for replacement of new cremators and mercury abatement equipment to be funded through a combination of the Mercury Abatement Reserve and borrowing be agreed.
Report author: Paul Holloway
Publication date: 09/02/2012
Date of decision: 09/02/2012
Decided at meeting: 09/02/2012 - Cabinet (pre 2012)
Effective from: 17/02/2012