Decision - Corporate Procurement of Electricity and Gas Supplies
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Corporate Procurement of Electricity and Gas Supplies
Decision Maker: Policy & Resources Committee (pre 2015)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
This report explains the options available for
the re-procurement of the council's electricity and gas
supplies.
Decision:
That the Committee grant delegated authority to the Assistant Director Property & Design–
(i) to award a contract effective from 1 October 2016 for a maximum period of four years for the Council’s large (over 50kW) electricity supplies from 100% renewable sources and gas supplies through a flexible framework agreement offered by the LASER Energy Buying Group;
(ii) to award a contract effective from 1 April 2016 for a maximum period of four years for the Council’s non half hourly (sub 50kW) electricity supplies from 100 percent renewable sources through a fixed compliant framework agreement;
(iii) to award a six-month bridging contract with the existing LASER flexible supplier to allow a proportion of the supplies referred to in 2.1 (ii) above to switch to a flexible arrangement from 1st October 2016.
Report author: Lisa Doody
Publication date: 12/02/2015
Date of decision: 12/02/2015
Decided at meeting: 12/02/2015 - Policy & Resources Committee (pre 2015)
Effective from: 20/02/2015