Decision - New Homes for Neighbourhoods - Final Scheme approval - Wellsbourne, Whitehawk
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
New Homes for Neighbourhoods - Final Scheme approval - Wellsbourne, Whitehawk
Decision Maker: Policy & Resources Committee (pre 2015)
Decision status: Recommendations approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Final approval for transfer of land, design
and scheme costs (Wellsbourne site)
Decision:
That the Committee be recommended to:
1) Approve that the land at Wellsbourne is appropriated to the HRA for a capital receipt of £360,000 for planning purposes and the development of new housing.
2) Approve a budget of £7.077m for the Wellsbourne scheme in the HRA Capital Programme which will be financed through a mixture of HRA borrowing and retained right-to-buy capital receipts.
Report author: Jaine Jolly
Publication date: 17/03/2016
Date of decision: 17/03/2016
Decided at meeting: 17/03/2016 - Policy & Resources Committee (pre 2015)
Accompanying Documents: