Decision - Moulsecoomb Hub & Housing Project Update
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Moulsecoomb Hub & Housing Project Update
Decision Maker: Policy & Resources Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Decision:
RESOLVED:
That Housing Committee:
2.1 Recommends to Policy & Resources committee that Policy & Resources Committee:
2.1.1. Notes the progress made on the Moulsecoomb Hub and Housing project to date
2.1.2. Authorises officers to progress RIBA stage 4 (technical design)
2.1.3. Approves an additional budget of £3.771m for this work, to be funded by HRA Borrowing and BLRF grant allocation and included as part of the 2022/23 HRA Capital Programme
2.1.4. Approves the grant-funded enabling works to commence, including the demolition of Moulsecoomb Hubs north and south, to be financed by £1.694m BLRF grant allocation
2.1.5. Confirms minor changes to the appropriation of land as approved at Policy & Resources Committee in November 2021 to include land around the buildings on site, and delegates authority to the Executive Director of Housing, Neighbourhood & Communities to approve further minor changes
That Policy & Resources Committee:
2.1.6. Notes the progress made on the Moulsecoomb Hub and Housing project to date.
2.1.7. Authorises officers to progress RIBA stage 4 (technical design)
2.1.8. Approves an additional budget of £3.771m for this work, to be funded by HRA Borrowing and BLRF grant allocation and included as part of the 2022/23 HRA Capital Programme
2.1.9. Approves the grant-funded enabling works to commence, including the demolition of Moulsecoomb Hubs north and south, to be financed by £1.694m BLRF grant allocation
2.1.10. Confirms minor changes to the appropriation of land as approved at Policy & Resources Committee in November 2021 to include land around the buildings on site, and delegates authority to the Executive Director of Housing, Neighbourhood & Communities to approve further minor changes.
Report author: Stephen Marsden
Publication date: 29/07/2022
Date of decision: 29/07/2022
Decided at meeting: 29/07/2022 - Policy & Resources Committee
Accompanying Documents:
- PR Extract from Housing Cmt - Item 12 - Moulsecoomb Neighbourhood Hub Housing Project PDF 127 KB View as HTML (1) 33 KB
- Moulsecoomb Hub & Housing Project Update PDF 367 KB View as HTML (2) 94 KB
- Moulsecoomb Hub & Housing Project Update APX2. n 1 PDF 2 MB
- Moulsecoomb Hub & Housing Project Update APX1. n 2 PDF 2 MB