Decision - Eastergate Road Former Garage Site Redevelopment

skip navigation and tools

Decision details

Eastergate Road Former Garage Site Redevelopment

Decision Maker: Policy & Resources Committee

Is Key decision?: No

Is subject to call in?: No

Purpose:

Approval of Scheme and Procurement of Main Contractor

Decision:

RESOLVED: That the Committee approved a budget for the former garage site at Eastergate Road of £293,000 to allow the completion of design work to the end of RIBA Stage 4 (technical design), and for site clearance works, financed by a mixture of HRA borrowing and Brownfield Land Release Fund (BLRF) grant.

Report author: Paul Dalton

Publication date: 01/12/2022

Date of decision: 01/12/2022

Decided at meeting: 01/12/2022 - Policy & Resources Committee