Royal Pavilion Estate Capital Project Phase 1
Decision Maker: Policy & Resources Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Up-date on project status and actions carried
out since the main contractor left site and stopped all works due
to insolvency
Decision:
RESOLVED: That the Committee
(i) Noted that the decision to appoint a contractor to complete
the stage 1 emergency and remedial works required to the buildings has been taken by the Executive Director for Economy, Environment & Culture.
(ii) Noted the recommendation of the Procurement Advisory
Board set out in paragraph 3.7.
(iii) Granted delegated authority to the Executive Director for
Economy, Environment & Culture to procure and award a contract for the stage 2 works required to complete the project as set out in paragraph 3.6.
(iv) Noted that Policy & Resources Committee approval to vary
the capital budget, via the Targeted Budget Management (TBM) reporting process, would be required as set out in paragraph 7.1.
Report author: Richard Davies
Publication date: 10/10/2019
Date of decision: 10/10/2019
Decided at meeting: 10/10/2019 - Policy & Resources Committee