Decision - Lanes car park - access arrangements
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Lanes car park - access arrangements
Decision Maker: Cabinet (pre 2012)
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
To inform Cabinet of revised scope and costs;
to seek approval to go ahead with a revised stair access and
adjustments to the existing lift area
Decision:
(1) That Cabinet to approve the allocation of £0.588m for the reconfiguration of pedestrian access and lift renovation to create a safer environment, meet modern standards, the councils regulatory obligations and policy commitments.
(2) That Cabinet retrospectively approves additional expenditure incurred of £0.440m, including the provision of six additional parking spaces (valued at circa £24k per annum).
(3) That authority be delegated to the Director of Environment to approve the appointment of a contractor to carry out works referred to in 2.1 above.
(4) That an offer be taken to the LDV Board within four weeks and that a letter be written to Board members confirming the timetable.
Reasons for the decision:
1. The recommended access reconfiguration will meet the council’s regulatory obligations and offer a cost saving over the option mentioned at 6.2.
2. The existing lift will be brought back to service and improved to meet modern standards.
3. The new access reconfiguration will deliver easier and safer access for car park users, a safer proposition for the Fire Service and will help to resolve the serious anti social issues associated with the site.
Alternative options considered:
Relocation of the lift was considered. This alternative was rejected, as it was more expensive (+£0.29m) and the detailed design and aesthetics were still to be determined.
Report author: Austen Hunter
Publication date: 14/01/2010
Date of decision: 14/01/2010
Decided at meeting: 14/01/2010 - Cabinet (pre 2012)
Effective from: 22/01/2010
Accompanying Documents: