Decision - Moulsecoomb Hub and Housing Project
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Moulsecoomb Hub and Housing Project
Decision Maker: Housing & New Homes Committee, Strategy, Finance & City Regeneration Committee
Is Key decision?: No
Is subject to call in?: No
Purpose:
An update on the Moulsecoomb project seeking
approval for a way forward
Decision:
RESOLVED:
That Housing and New Homes Committee
Recommends to Strategy, Finance & City Regeneration Committee to:
2.1 Agree to begin a procurement exercise for the redevelopment of this site, including early market engagement.
2.2 Delegate authority to the Executive Director of Environment, Economy & Culture and the Executive Director Housing, Neighbourhoods &
Communities to procure the contractors and then once a budget has been agreed at a subsequent committee meeting, to then enter in to relevant contracts.
2.3 Note that the demolition of some of the existing buildings is due to
commence in March 2024.
That Strategy, Finance & City Regeneration Committee:
2.1 Agree to begin a procurement exercise for the redevelopment of this site, including early market engagement.
2.2 Delegate authority to the Executive Director of Environment, Economy & Culture and the Executive Director Housing, Neighbourhoods &
Communities to procure the contractors and then once a budget has been agreed at a subsequent committee meeting, to then enter in to relevant contracts.
2.3 Note that the demolition of some of the existing buildings is due to
commence in March 2024.
Report author: Stephen Marsden
Publication date: 14/03/2024
Date of decision: 14/03/2024
Decided at meeting: 14/03/2024 - Strategy, Finance & City Regeneration Committee