Targeted Budget Management (TBM) Capital Outturn 2007/08
Meeting: 12/06/2008 - Cabinet (pre 2012) (Item 15)
15 Targeted Budget Management (TBM) Capital Outturn 2007/08 PDF 173 KB
Decision:
1. That the changes to the capital budget, as set out in Appendix 1 of the report be approved.
2. That it be noted that the programme slipped by 3.48%, as set out in paragraph 3.3 of the report.
3. That the carrying forward of 2007/08 slippage (£1.407 million) into the 2008/09 capital programme, to meet on-going commitments on these schemes, be approved.
Minutes:
15.1 The Cabinet considered a report of the Director of Finance & Resources concerning the revenue the capital outturn for 2007/08; it also offered information regarding programme slippage, budget changes and sought approval for carry forward to the 2008/09 programme (for copy see minute book).
15.2 In response to questions from Councillor Mitchell, Councillor Theobald reported that repairs to the Bandstand would not jeopardise current budget projections.
15.3 RESOLVED – Having considered the information and the reasons set out in the report, the Cabinet accepted the following recommendations:
(1) That the changes to the capital budget, as set out in Appendix 1 of the report be approved.
(2) That it be noted that the programme slipped by 3.48%, as set out in paragraph 3.3 of the report.
(3) That the carrying forward of 2007/08 slippage (£1.407 million) into the 2008/09 capital programme, to meet on-going commitments on these schemes, be approved.