Corporate Procurement of Electricity and Gas Supplies
Meeting: 12/02/2015 - Policy & Resources Committee (pre 2015) (Item 146)
146 Corporate Procurement of Electricity and Gas Supplies PDF 105 KB
Report of the Interim Executive Director for Finance & Resources (copy attached).
Additional documents:
Decision:
That the Committee grant delegated authority to the Assistant Director Property & Design–
(i) to award a contract effective from 1 October 2016 for a maximum period of four years for the Council’s large (over 50kW) electricity supplies from 100% renewable sources and gas supplies through a flexible framework agreement offered by the LASER Energy Buying Group;
(ii) to award a contract effective from 1 April 2016 for a maximum period of four years for the Council’s non half hourly (sub 50kW) electricity supplies from 100 percent renewable sources through a fixed compliant framework agreement;
(iii) to award a six-month bridging contract with the existing LASER flexible supplier to allow a proportion of the supplies referred to in 2.1 (ii) above to switch to a flexible arrangement from 1st October 2016.
Minutes:
146.1. RESOLVED: That the Assistant Director Property & design be granted delegated authority:
(i) To award a contract effective from 1 October 2016 for a maximum period of four years for the Council’s large (over 50kW) electricity supplies from 100% renewable sources and gas supplies through a flexible framework agreement offered by the LASER Energy Buying Group;
(ii) To award a contract effective from 1 April 2016 for a maximum period of four years for the Council’s non half hourly (sub 50kW) electricity supplies from 100 percent renewable sources through a fixed compliant framework agreement; and
(iii) To award a six-month bridging contract with the existing LASER flexible supplier to allow a proportion of the supplies referred to in 2.1 (ii) above to switch to a flexible arrangement from 1st October 2016.