Issue - items at meetings - New Homes for Neighbourhoods - Windlesham House

skip navigation and tools

Issue - meetings

New Homes for Neighbourhoods - Windlesham House

Meeting: 23/06/2021 - Housing Committee (Item 10)

10 New Homes for Neighbourhoods - Windlesham House pdf icon PDF 324 KB

Additional documents:

Decision:

RESOLVED:

 

Housing Committee:

 

2.1      That the proposals to demolish Windlesham House and develop 17 new council homes at Windlesham Close, Portslade, under the NHFN programme be approved; and

 

2.2      That it be agreed that the project proceeds through the City Build Partnership, the council’s Strategic Construction Partnership with Morgan Sindall.

 

2.3      That Policy & Resources Committee be recommended to approve a capital budget of up to £5.300m to be included in the 2021/22 HRA Capital Programme and financed by HRA Borrowing, Land Release Grant funding and HRA capital receipts.

 

Policy & Resources Committee:

 

2.4      That a HRA Capital budget of up to £5.300m financed by HRA Borrowing, Land Release Grant funding and HRA capital receipts be approved, to be included in the 2021/22 HRA Capital Programme.

Minutes:

10.1    The Estate Regeneration Project Manager introduced the report to the committee.

 

          Questions

 

10.2    Councillor Williams was informed that parking and one unit would be lost to the development if a community space was included in the proposals. The viability of the project would be affected if the number of units were reduced. It was noted that the are several community spaces in the area.

 

10.3    Councillor Meadows was informed that the rents would not be decided at this committee meeting and the local rents were cost affective regarding the business plan model.

 

          Vote

 

10.4    A vote was taken, and unanimously the committee agreed the recommendations.  

 

RESOLVED:

 

Housing Committee:

 

2.1      That the proposals to demolish Windlesham House and develop 17 new council homes at Windlesham Close, Portslade, under the NHFN programme be approved; and

 

2.2      That it be agreed that the project proceeds through the City Build Partnership, the council’s Strategic Construction Partnership with Morgan Sindall.

 

2.3      That Policy & Resources Committee be recommended to approve a capital budget of up to £5.300m to be included in the 2021/22 HRA Capital Programme and financed by HRA Borrowing, Land Release Grant funding and HRA capital receipts.

 

Policy & Resources Committee:

 

2.4      That a HRA Capital budget of up to £5.300m financed by HRA Borrowing, Land Release Grant funding and HRA capital receipts be approved, to be included in the 2021/22 HRA Capital Programme.


 


Brighton & Hove City Council | Hove Town Hall | Hove | BN3 3BQ | Tel: (01273) 290000 | Mail: info@brighton-hove.gov.uk | how to find us | comments & complaints