Targeted Budget Management (TBM) 2025/26 Month 2 (May)
18/07/2025 - Targeted Budget Management (TBM) 2025/26 Month 2 (May)
1) Cabinet notes the forecast risk position for the General Fund, which indicates a potential forecast overspend risk of £15.486m.
2) Cabinet notes the forecast overspend risk for the separate Housing Revenue Account (HRA), which is an overspend of £0.450m.
3) Cabinet notes the forecast overspend risk for the ring-fenced Dedicated Schools Grant, which is an overspend of £4.437m.
4) Cabinet notes the forecast position on the Capital Programme which is an underspend variance of £0.417m.
5) Cabinet approves the capital budget variations and re-profiling requests set out in Appendix 5.
6) Cabinet approves the new capital schemes requested in Appendix 6.