Targeted Budget Management (TBM) 2025/26 Month 5 (August)
17/10/2025 - Targeted Budget Management (TBM) 2025/26 Month 5 (August)
1) Cabinet notes the forecast risk position for the General Fund, which indicates a potential forecast overspend risk of £9.406m.
2) Cabinet notes the forecast overspend risk for the separate Housing Revenue Account (HRA), which is an overspend of £1.192m.
3) Cabinet notes the forecast overspend risk for the ring-fenced Dedicated Schools Grant, which is an overspend of £2.843m.
4) Cabinet notes the forecast position on the Capital Programme which is an underspend variance of £5.901m.
5) Cabinet approves the capital budget variations and re-profiling requests set out in Appendix 6.
6) Cabinet approves the new capital schemes requested in Appendix 7.
7) Cabinet notes the Treasury Management update as set out in Appendix 8 and summarised in paragraph 9.
8) Cabinet notes the strategic decisions being considered to reshape the city’s approach to temporary accommodation and establish long-term financial sustainability and that reports outlining these proposals in detail will be presented to Cabinet for consideration at a future date.
9) Cabinet agrees to extend existing and future lease arrangements for Temporary Accommodation to at least 10 years and 1 day where appropriate, and delegate authority to Corporate Director – Homes & Adult Social Care, in consultation with the Lead Member for Housing, to implement.
10) Cabinet agrees the set of Strategic Aims in Appendix 9 for the purpose of Direct Offers, in effect until 31 March 2026 and reviewed in January 2026.