Decisions for issue Planned Maintenance Budget Allocation 2012-13 and Programme of Works for the Council’s Operational Buildings
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details : Issue
Issue - decisions
Planned Maintenance Budget Allocation 2012-13 and Programme of Works for the Council’s Operational Buildings
15/03/2012 - Planned Maintenance Budget Allocation 2012-13 and Programme of Works for the Council’s Operational Buildings
(1) That the financial allocation to an annual programme of works to the operational buildings at an estimated cost of £4,060,000 as detailed in Appendices A and B, to the report, in accordance with Financial Regulation A.5.6.7 be approved; and
(2) That delegated authority, where necessary, be granted to the Strategic Director; Resources to enter into contracts within this budget which are procured in accordance with Contract Standing Orders.