Decisions for issue Madeira Terrace Restoration - Petition response and next steps
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Issue
Issue - decisions
Madeira Terrace Restoration - Petition response and next steps
21/06/2019 - Madeira Terrace Restoration - Petition response and next steps
1) That the Committee delegates authority to the Executive Director for Economy, Environment & Culture to procure and award a contract for early design stage work (RIBA 0-1) and engineering of 30 out of a total of 151 Madeira Terrace arches and instructs officers to include a requirement in the contract that the use of innovative renewable technology such as solar panels and rainwater harvesting should be made a priority to reduce costs in the long-term and help the city to meet its commitment to achieving a carbon neutral status by 2030.
2) That the Committee instructs the Executive Director for Economy, Environment & Culture to bring a report to the November committee outlining proposals to use the crowdfunded funds (alongside the allocated council funding if required) to progress plans for the development of an initial three arches
- to showcase what is possible and;
- to gain a deeper understanding of the technical challenges that may present themselves during the development of subsequent arches;
-
with the intention that plans are progressed to
develop the initial three arches, to similar sustainability
standards, without waiting for funds to be available to develop the
30 arches as described in 2.1.
This report should contain options for which three arches should be progressed and developed, including an option of the three arches directly outside Concorde 2 and an assessment of the business case for leasing these to Concorde 2 as they have suggested.