The King Alfred Leisure Centre Regeneration Project
This report will set out options for delivering a new leisure centre in the west of the city. Cabinet will be asked to consider the site and delivery options.
Decision type: Key
Reason Key: Expenditure is greater than £1,000,000 & Significant impact on 2 or more Wards;
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 18/06/2024
Decision due: 18 Jul 2024 by Cabinet
Lead member: Cabinet Member for Sports & Recreation
Lead director: Corporate Director for City Services
Contact: Mark Healy, City Regeneration Programme Manager Email: Mark.Healy@brighton-hove.gov.uk, Sophie Sargeant, Sports Facilities Programme Manager Email: Sophie.Sargeant@brighton-hove.gov.uk.
Consultation process
Comprehensive engagement and consultation has
taken place throughout the life of the project, beginning shortly
after project inception in Autumn 2022. There have been three key
phases so far, these being:
• First phase, from September 2022 focused on meeting with
King Alfred’s sports clubs, leaseholders, and other regular
users
• Second phase, from January 2023, which expanded engagement
to reach out to community groups and groups representing the
diversity of the city.
o Trust for Developing Communities commissioned to undertake
engagement programme for young people and minoritised ethnic
groups.
o Reference group established.
o Drop-in event & visioning workshop held in spring.
• Third phase launched January. Officers launched the on-line
questionnaire from 8 January to 16 February, which was supported by
updated website, information booklet, drop-in events, maildrops,
social media campaign, and other promotional activities. Over 3,600
questionnaires completed and returned along with additional
comments to the project mailbox.
Decisions
- 19/07/2024 - King Alfred Leisure Centre Regeneration Project
Agenda items
- 18/07/2024 - Cabinet King Alfred Leisure Centre Regeneration Project 18/07/2024
Documents
- Delivery options for the King Alfred Redevelopment Project including leisure contract reprocurement .