Valley Gardens Phase 3 project update
As noted in the recommendations for Valley Gardens Phase 3 (February 2019 ETS Report), a third public consultation process has now been conducted. Furthermore, stakeholder engagement design workshops have also taken place across key stakeholder focus groups. The new City Transport Professional Services Framework has been used to tender and procure a contract, and appoint a consultant, to work with council officers to progress the scheme design. This report updates members on the initial outcomes of these processes, and outlines the next steps of the project.
Decision type: Non-key
Decision status: Recommendations Approved
Wards affected: Queen's Park; Regency; St Peter's & North Laine;
Notice of proposed decision first published: 01/02/2021
Decision due: 16 Mar 2021 by Environment, Transport & Sustainability Committee
Lead director: Executive Director, Economy, Environment & Culture
Contact: Oliver Spratley Email: oliver.spratley@brighton-hove.gov.uk Tel: 01273 290390.
Decisions
- 17/03/2021 - Valley Gardens Phase 3 project update
Agenda items
- 16/03/2021 - Environment, Transport & Sustainability Committee Valley Gardens Phase 3 project update 16/03/2021
Documents
- Valley Gardens Phase 3 project update